The solar farm near Long Stratton now forecasts 154 lorry movements a day on parts of the A140 at peak, up from 67. Its change request is due on 20 November.
The developer of East Pye Solar, the 500-megawatt solar farm planned near Long Stratton, now expects far more lorries on local roads while it is built. Its new forecast more than doubles peak lorry movements on the A140 either side of the B1527 junction, from 67 a day to 154.
The figures are in a change notification East Pye Solar Limited sent to the Planning Inspectorate on 30 October. The inspectorate published it on 4 November. Long Stratton is about eight miles south-east of Wymondham.
Overview
- The developer has raised its forecast of construction lorries on 20 roads around the scheme.
- The biggest rise is on the B1527, from 38 lorry movements a day to 132.
- It also wants to add a temporary construction compound at Sub-site 7F.
- It plans to submit the formal change request on 20 November 2026.
- If the change is accepted, anyone registered in the examination can comment by 6 January 2027.
Why the forecast went up
The developer says it has changed how it counts construction traffic, not where the lorries go. The new method was worked up on another Island Green Power scheme, West Burton Solar, after detailed design and talks with construction contractors.
The notification says the routing strategy is unchanged. Forecasts for vans and other light vehicles are also unchanged. All of the increase is in heavy goods vehicles.
The largest rises are on roads serving the sites with substations and battery storage. The developer names the B1527, the B1134 and parts of the A140.
The roads with the biggest rises
The figures are two-way movements a day at the peak of construction. The transport chapter of the application treats them as a worst case, with all construction work happening at once.
| Road | Lorries a day before | Lorries a day now | Increase |
|---|---|---|---|
| B1527 | 38 | 132 | +94 |
| A140 north of the B1527 | 67 | 154 | +87 |
| A140 south of the B1527 | 67 | 154 | +87 |
| A140 south of the B1134 | 67 | 154 | +87 |
| B1134 | 38 | 106 | +68 |
| B1332 (south) | 70 | 120 | +50 |
| Fairstead Lane (west) | 22 | 56 | +34 |
| The Krons | 22 | 56 | +34 |
| Harvey Lane | 14 | 42 | +28 |
The table comes from Table 7-1 of the change notification. On the A140 north of the B1527, total construction traffic would rise from 295 vehicles a day to 382.
The application’s transport chapter says that stretch passes the eastern edge of Tasburgh and Upper Tasburgh. It describes the A140 south of the B1527 as passing residential and commercial areas with high pedestrian footfall.
A compound that was dropped, now back
The second change adds a temporary construction and decommissioning laydown area at Sub-site 7F. The developer showed a similar compound at nearby Site 7D at its statutory consultation. It was left out of the final application as the design developed.
The developer says neither change needs extra land beyond the scheme’s current boundary.
What the inspectors said
The Examining Authority replied on 4 November. Its letter says it is minded to agree the changes do not make it a materially different project. It cannot decide that until the full change request arrives.
It also told the developer:
- to explain why the compound was not in the original application
- to publish a map showing every road affected by the new traffic figures
- to reassess noise, air quality, footpaths and the construction traffic plan where the traffic changes
- that nine days of consultation with Site 7 landowners and parish councils was too short, against the advised minimum of 28 days
The developer’s own timetable had that consultation running from 4 to 13 November.
The timetable from here
The examination timetable shows these dates:
- Wednesday 18 November: compulsory acquisition hearing
- Thursday 19 November: accompanied site inspection
- Friday 20 November: the developer plans to submit the change request
- Tuesday 24 November: Deadline 3 for written submissions
- 15 to 18 December: issue specific hearings on environmental matters and the draft order
- 6 January 2027: Deadline 4, including comments on the change request
- 23 February 2027: the examination is due to close
The December hearings are at Dunston Hall, Ipswich Road, Norwich NR14 8PQ, and online. They start at 10am on Tuesday 15 December. The Examining Authority will decide whether to accept the change before then.
The scheme would cover land near Long Stratton and connect to the 400kV power line between Norwich Main and Bramford substations, according to the developer. The final decision rests with the Secretary of State, after the inspectors report.
What it means for you
- If you drive the A140 between Norwich and Long Stratton, or the B1527, expect more lorries during construction than first forecast. No start date has been set, because the scheme does not yet have consent.
- If you registered to take part in the examination, you can comment on the change by 6 January 2027, once the inspectors accept it.
- The hearings are public. The project page carries livestream links and recordings.
Sources
- East Pye Solar change notification, Revision 1, October 2026 (EXAM/9.37, AS-041): the two changes, Table 5-1 timetable and Table 7-1 traffic forecasts.
- Examining Authority’s response to the change notification, 4 November 2026.
- Environmental Statement Chapter 11, Transport and Access: daily two-way flows at peak construction and the road descriptions.
- Examination timetable and hearing notification for December, 16 November 2026, Planning Inspectorate, read 18 November 2026.
Have your say